Dept. of Trans. PROGRESS Serial No. Contract No. 10-260-08-05 10-363124 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 11% 10-MER-99-10.8/13.1 Federal Project: NONE Progress payment No. 06 Payment period ending: 09-17-10 TAKEHARA LANDSCAPE INC P O BOX 277085 SACRAMENTO CA 95827 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 497,841.00 259,034.75 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 497,841.00 259,034.75 5. Mobilization 5,204.60 260.23 6. Total Work Completed 503,045.60 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 503,045.60 259,294.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 259,294.98