Dept. of Trans. PROGRESS Serial No. Contract No. 13-165-08-30 10-363124 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 79% 10-MER-99-10.8/13.1 Federal Project: NONE Progress payment No. 38 Payment period ending: 06-20-13 TAKEHARA LANDSCAPE INC P O BOX 277085 SACRAMENTO CA 95827 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 908,796.30 4,384.80 2.a. Extra Work 30,494.99 0.00 b. Adjustment Comp. 4,384.04 0.00 3. Materials on Hand 4. Earned Subject to Retention 943,675.33 4,384.80 5. Mobilization 5,204.60 0.00 6. Total Work Completed 948,879.93 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 948,879.93 4,384.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,384.80