Dept. of Trans. PROGRESS Serial No. Contract No. 14-199-09-54 10-381514 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 20% 25% 10-MER-165-26.7/30.0 Federal Project: 10-MER-140-16.2/ .0 STP-P165(12) Progress payment No. 02 Payment period ending: 07-20-14 A. TEICHERT & SON INC. DBA TEICHERT CONSTRUCTION P O BOX 520 FOWLER, CA 93625-0520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 552,101.58 275,006.40 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 552,101.58 275,006.40 5. Mobilization 307,500.00 102,500.00 6. Total Work Completed 859,601.58 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 859,601.58 377,506.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 377,506.40