Dept. of Trans. SEMI-FINAL Serial No. Contract No. 15-065-08-47 10-381514 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-MER-165-26.7/30.0 STP-P165(12) 10-MER-140-16.2 Progress payment No. 009 Payment period ending: 01-21-15 A. TEICHERT & SON INC. DBA TEICHERT CONSTRUCTION P O BOX 520 FOWLER, CA 93625-0520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,568,526.32 1,000.00 2. a. Extra Work 247,085.19 140,965.10 b. Adustment Comp. 35,345.48 37,911.00 3. Materials on Hand 4. Earned Subject to Retention 3,850,956.99 179,876.10 5. Mobilization 410,000.00 0.00 6. Total Work Completed 4,260,956.99 7. Deductions -18,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,242,956.99 179,876.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 179,876.10