Dept. of Trans. PROGRESS Serial No. Contract No. 15-054-08-14 10-3A1004 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 58% Location: Federal Project: 10-SJ-4-R19.5/R20.1 NONE 10-SJ-99-15.0/18.6 Progress payment No. 025 Payment period ending: 02-20-15 MYERS AND SONS CONSTRUCTION LP 2554 MILLCREEK DRIVE SACRAMENTO CA 95833 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 30,936,820.81 330,412.33 2. a. Extra Work 3,059,940.39 190,325.94 b. Adustment Comp. 2,979,815.25 6,877.69 3. Materials on Hand 1,822,253.93 5,618.80 4. Earned Subject to Retention 38,798,830.38 533,234.76 5. Mobilization 6,460,000.00 0.00 6. Total Work Completed 43,436,576.45 7. Deductions -133,441.61 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 45,125,388.77 533,234.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 533,234.76