Dept. of Trans. PROGRESS Serial No. Contract No. 15-110-13-40 10-3A1004 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 60% Location: Federal Project: 10-SJ-4-R19.5/R20.1 NONE 10-SJ-99-15.0/18.6 Progress payment No. 027 Payment period ending: 04-20-15 MYERS AND SONS CONSTRUCTION LP 4600 NORTHGATE BLVD., STE 100 SACRAMENTO, CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 33,783,419.69 1,499,104.70 2. a. Extra Work 3,332,856.34 22,047.61 b. Adustment Comp. 3,047,799.86 -24,991.23 3. Materials on Hand 1,755,558.20 15,996.26 4. Earned Subject to Retention 41,919,634.09 1,512,157.34 5. Mobilization 6,460,000.00 0.00 6. Total Work Completed 46,624,075.89 7. Deductions -508,217.79 -379,776.18 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 47,871,416.30 1,132,381.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,132,381.16