Dept. of Trans. PROGRESS Serial No. Contract No. 15-261-10-00 10-3A1004 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 72% Location: Federal Project: 10-SJ-4-R19.5/R20.1 NONE 10-SJ-99-15.0/18.6 Progress payment No. 032 Payment period ending: 09-20-15 MYERS AND SONS CONSTRUCTION LP 4600 NORTHGATE BLVD., STE 100 SACRAMENTO, CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 47,666,172.15 2,734,501.94 2. a. Extra Work 4,581,168.04 130,676.98 b. Adustment Comp. 3,836,154.17 190,355.65 3. Materials on Hand 986,203.68 362,237.88 4. Earned Subject to Retention 57,069,698.04 3,417,772.45 5. Mobilization 6,800,000.00 0.00 6. Total Work Completed 62,883,494.36 7. Deductions -130,171.45 35,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 63,739,526.59 3,452,772.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,452,772.45