Dept. of Trans. PROGRESS Serial No. Contract No. 16-208-14-53 10-3A1004 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 87% Location: Federal Project: 10-SJ-4-R19.5/R20.1 NONE 10-SJ-99-15.0/18.6 Progress payment No. 043 Payment period ending: 07-20-16 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 63,226,271.21 1,922,182.68 2. a. Extra Work 6,556,797.86 294,464.42 b. Adustment Comp. 4,870,775.27 -111,762.98 3. Materials on Hand 382,343.91 57,932.03 4. Earned Subject to Retention 75,036,188.25 2,162,816.15 5. Mobilization 6,800,000.00 0.00 6. Total Work Completed 81,453,844.34 7. Deductions -277,871.45 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 81,558,316.80 2,152,816.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,152,816.15