Dept. of Trans. PROGRESS Serial No. Contract No. 16-263-09-50 10-3A1004 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 92% Location: Federal Project: 10-SJ-4-R19.5/R20.1 NONE 10-SJ-99-15.0/18.6 Progress payment No. 045 Payment period ending: 09-20-16 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 67,902,052.50 3,645,471.84 2. a. Extra Work 7,335,577.91 264,564.32 b. Adustment Comp. 5,027,335.14 -450,442.32 3. Materials on Hand 116,099.75 -24,720.44 4. Earned Subject to Retention 80,381,065.30 3,434,873.40 5. Mobilization 6,800,000.00 0.00 6. Total Work Completed 87,064,965.55 7. Deductions -690,862.95 -502,991.50 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 86,490,202.35 2,931,881.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,931,881.90