Dept. of Trans. PROGRESS Serial No. Contract No. 16-328-11-06 10-3A1004 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 96% Location: Federal Project: 10-SJ-4-R19.5/R20.1 NONE 10-SJ-99-15.0/18.6 Progress payment No. 048 Payment period ending: 11-20-16 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 71,219,232.04 1,014,379.16 2. a. Extra Work 7,898,020.65 355,363.59 b. Adustment Comp. 5,134,318.89 153,504.24 3. Materials on Hand 17,943.95 -9,302.12 4. Earned Subject to Retention 84,269,515.53 1,513,944.87 5. Mobilization 6,800,000.00 0.00 6. Total Work Completed 91,051,571.58 7. Deductions -180,862.95 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 90,888,652.58 1,513,944.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,513,944.87