Dept. of Trans. PROGRESS Serial No. Contract No. 20-324-11-14 10-3A1014 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 20% Location: Federal Project: 10-SJ-99-16.4/18.2 STPL-6210(13) Progress payment No. 003 Payment period ending: 11-20-20 WABO LANDSCAPE & CONSTRUCTION INC 726 ALFRED NOBEL DR HERCULES CA 94547 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 696,583.00 195,084.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 696,583.00 195,084.00 5. Mobilization 216,600.00 0.00 6. Total Work Completed 913,183.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 913,183.00 195,084.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 195,084.00