Dept. of Trans. PROGRESS Serial No. Contract No. 07-142-09-53 10-3A1204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 18% 10-SJ-5-R13.9/R15.6 Federal Project: NONE Progress payment No. 05 Payment period ending: 05-20-07 NEHEMIAH CONSTRUCTION INC 4790 E 2ND STREET BENICIA CA 94501 Escrow No. 02294 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,546,823.40 1,050,853.90 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4,023.76 -304,602.24 4. Earned Subject to Retention 4,550,847.16 746,251.66 5. Mobilization 1,149,500.00 0.00 6. Total Work Completed 5,696,323.40 7. Deductions -479.70 -479.70 8. a.Contract Retentions -235,614.60 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,464,252.86 745,771.96 10. Reduction Amt to Escrow 11. Payment to Escrow 235,610.00 12. Net Pymt. this Estimate 745,771.96