Dept. of Trans. PROGRESS Serial No. Contract No. 08-023-08-24 10-3A1204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 71% 51% 10-SJ-5-R13.9/R15.6 Federal Project: NONE Progress payment No. 13 Payment period ending: 01-20-08 NEHEMIAH CONSTRUCTION INC 4790 E 2ND STREET BENICIA CA 94501 Escrow No. 02294 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,033,443.00 326,344.20 2.a. Extra Work 173,372.27 15,357.01 b. Adjustment Comp. 30,120.00 0.00 3. Materials on Hand 0.00 -20,658.69 4. Earned Subject to Retention 8,236,935.27 321,042.52 5. Mobilization 1,210,000.00 0.00 6. Total Work Completed 9,446,935.27 7. Deductions -255,479.70 0.00 8. a.Contract Retentions -411,846.76 -16,052.12 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,779,608.81 304,990.40 10. Reduction Amt to Escrow 11. Payment to Escrow 411,840.00 12. Net Pymt. this Estimate 304,990.40