Dept. of Trans. PROGRESS Serial No. Contract No. 08-143-07-54 10-3A1204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 68% 10-SJ-5-R13.9/R15.6 Federal Project: NONE Progress payment No. 17 Payment period ending: 05-20-08 NEHEMIAH CONSTRUCTION INC 801 FIRST STREET, STE. G BENICIA CA 94510 Escrow No. 02294 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,438,349.20 419,091.80 2.a. Extra Work 375,946.92 92,466.65 b. Adjustment Comp. 30,120.00 0.00 3. Materials on Hand 20,658.69 0.00 4. Earned Subject to Retention 9,865,074.81 511,558.45 5. Mobilization 1,210,000.00 0.00 6. Total Work Completed 11,054,416.12 7. Deductions -479.70 0.00 8. a.Contract Retentions -493,253.74 -25,577.92 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,581,341.37 485,980.53 10. Reduction Amt to Escrow 11. Payment to Escrow 493,250.00 12. Net Pymt. this Estimate 485,980.53