Dept. of Trans. FINAL Serial No. Contract No. 12-172-09-25 10-3A1204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-SJ-5-R13.9/R15.6 Federal Project: NONE Progress payment No. 27 Payment period ending: 11-07-08 NEHEMIAH CONSTRUCTION INC 801 FIRST STREET, STE. G BENICIA CA 94510 Escrow No. 02294 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,784,473.89 0.00 2.a. Extra Work 610,660.98 0.00 b. Adjustment Comp. 107,176.47 -6,683.00 3. Materials on Hand 4. Earned Subject to Retention 12,502,311.34 -6,683.00 5. Mobilization 1,210,000.00 0.00 6. Total Work Completed 13,712,311.34 7. Deductions -479.70 0.00 8. a.Contract Retentions -598,958.12 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 598,958.12 0.00 9. Total pay to Contractor 13,711,831.64 -6,683.00 10. Reduction Amt to Escrow -598,950.00 0.00 11. Payment to Escrow 598,950.00 12. Net Pymt. this Estimate -6,683.00