Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-312-13-25 10-3A2304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-SJ-12-0.0/0.1 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-25-07 TRUESDELL CORPORATION OF CALIFORNIA INC 1310 W 23RD STREET TEMPE AZ 85282 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 96,327.20 70,829.20 2.a. Extra Work 27,282.24 27,282.24 b. Adjustment Comp. -40,688.00 -40,688.00 3. Materials on Hand 4. Earned Subject to Retention 82,921.44 57,423.44 5. Mobilization 20,128.60 9,534.60 6. Total Work Completed 103,050.04 7. Deductions -11,228.99 -11,228.99 8. a.Contract Retentions -1,337.93 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 1,337.93 1,337.93 9. Total pay to Contractor 91,821.05 57,066.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 57,066.98