Dept. of Trans. PROGRESS Serial No. Contract No. 09-327-14-35 10-3A6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 53% 10-STA-132-L14.9/L16.8 Federal Project: NH Progress payment No. 05 Payment period ending: 11-20-09 TEICHERT CONSTRUCTION P O BOX 3367 TURLOCK CA 95381 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 815,371.30 250,197.40 2.a. Extra Work 61,366.71 39,578.66 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 876,738.01 289,776.06 5. Mobilization 120,000.00 0.00 6. Total Work Completed 996,738.01 7. Deductions 0.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 996,738.01 299,776.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 299,776.06