Dept. of Trans. PROGRESS Serial No. Contract No. 11-168-13-23 10-3A66U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 1% 1% 10-MER-140-36.5/37.6 Federal Project: ACNH-P140(31) Progress payment No. 02 Payment period ending: 06-17-11 R G W CONSTRUCTION INC 550 GREENVILLE ROAD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 103,726.00 103,726.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 325,882.37 81,283.97 4. Earned Subject to Retention 429,608.37 185,009.97 5. Mobilization 6. Total Work Completed 103,726.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 429,608.37 185,009.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 185,009.97