Dept. of Trans. PROGRESS Serial No. Contract No. 12-142-10-45 10-3A66U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 25% 10-MER-140-36.5/37.6 Federal Project: ACNH-P140(31) Progress payment No. 14 Payment period ending: 05-20-12 R G W CONSTRUCTION INC 550 GREENVILLE ROAD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,953,714.96 -189,171.41 2.a. Extra Work 897,409.92 694,864.75 b. Adjustment Comp. 33,230.31 0.00 3. Materials on Hand 660,250.12 -570.93 4. Earned Subject to Retention 7,544,605.31 505,122.41 5. Mobilization 1,740,400.00 0.00 6. Total Work Completed 8,624,755.19 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,285,005.31 505,122.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 505,122.41