Dept. of Trans. PROGRESS Serial No. Contract No. 12-236-08-09 10-3A66U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 48% 32% 10-MER-140-36.5/37.6 Federal Project: ACNH-P140(31) Progress payment No. 17 Payment period ending: 08-20-12 R G W CONSTRUCTION INC 550 GREENVILLE ROAD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,933,757.20 -110,392.98 2.a. Extra Work 1,493,960.82 500,744.00 b. Adjustment Comp. 39,380.31 0.00 3. Materials on Hand 635,782.02 -3,613.03 4. Earned Subject to Retention 9,102,880.35 386,737.99 5. Mobilization 1,740,400.00 0.00 6. Total Work Completed 10,207,498.33 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,843,280.35 386,737.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 386,737.99