Dept. of Trans. PROGRESS Serial No. Contract No. 13-354-09-14 10-3A66U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 78% 61% 10-MER-140-36.5/37.6 Federal Project: ACNH-P140(31) Progress payment No. 34 Payment period ending: 12-20-13 R G W CONSTRUCTION INC 550 GREENVILLE ROAD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,479,564.19 607,436.45 2.a. Extra Work 2,373,273.04 26,680.52 b. Adjustment Comp. 122,852.61 0.00 3. Materials on Hand 375,325.38 -47,463.17 4. Earned Subject to Retention 16,351,015.22 586,653.80 5. Mobilization 1,832,000.00 0.00 6. Total Work Completed 17,807,689.84 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,183,015.22 586,653.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 586,653.80