Dept. of Trans. SEMI-FINAL Serial No. Contract No. 10-098-09-32 10-3A7404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-STA-108-22.4/26.5 Federal Project: ACST-P108(45) P-P108(45) Progress payment No. 20 Payment period ending: 03-12-10 GEORGE REED INC P O BOX 4760 MODESTO CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,961,468.94 -7,430.00 2.a. Extra Work 469,250.48 0.00 b. Adjustment Comp. -299,484.61 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,131,234.81 -7,430.00 5. Mobilization 21,000.00 0.00 6. Total Work Completed 6,152,234.81 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,147,234.81 -12,430.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -12,430.00