Dept. of Trans. PROGRESS Serial No. Contract No. 12-231-08-07 10-414824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 75% 10-MER-99-24.4/R25.8 Federal Project: NONE Progress payment No. 07 Payment period ending: 08-20-12 ENVIRONMENTAL LANDSCAPE SOLUTIONS 8380 ROVANA CIRCLE SACRAMENTO CA 95828 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 391,973.15 5,942.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 391,973.15 5,942.50 5. Mobilization 58,000.50 0.00 6. Total Work Completed 449,973.65 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 449,973.65 5,942.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,942.50