Dept. of Trans. PROGRESS Serial No. Contract No. 13-080-09-00 10-415704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 17% 10-MER-99-4.6/10.5 Federal Project: NONE Progress payment No. 09 Payment period ending: 03-20-13 TEICHERT/FLATIRON WEST A JOINT VENTURE P O BOX 1118 STOCKTON CA 95201 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,505,413.65 2,227,467.96 2.a. Extra Work 91,209.65 10,186.76 b. Adjustment Comp. 5,391,716.76 0.00 3. Materials on Hand 994,012.55 -252,736.02 4. Earned Subject to Retention 16,982,352.61 1,984,918.70 5. Mobilization 6,342,200.00 0.00 6. Total Work Completed 22,330,540.06 7. Deductions -18,213.87 30,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,306,338.74 2,014,918.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,014,918.70