Dept. of Trans. PROGRESS Serial No. Contract No. 13-140-09-06 10-415804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 19% 10-MER-99-0.0/4.6 Federal Project: NONE Progress payment No. 06 Payment period ending: 05-20-13 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,423,460.82 2,063,781.10 2.a. Extra Work 16,347.14 16,347.14 b. Adjustment Comp. 3. Materials on Hand 74,204.28 74,204.28 4. Earned Subject to Retention 5,514,012.24 2,154,332.52 5. Mobilization 603,750.00 201,250.00 6. Total Work Completed 6,043,557.96 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,107,762.24 2,345,582.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,345,582.52