Dept. of Trans. PROGRESS Serial No. Contract No. 15-051-13-09 10-415804 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 72% Location: Federal Project: 10-MER-99-0.0/4.6 NONE Progress payment No. 030 Payment period ending: 02-20-15 SECURITY PAVING COMPANY INC 13170 TELFAIR AVENUE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 33,330,396.39 333,672.18 2. a. Extra Work 546,080.94 6,960.49 b. Adustment Comp. 364,739.70 0.00 3. Materials on Hand 322,869.13 42,533.91 4. Earned Subject to Retention 34,564,086.16 383,166.58 5. Mobilization 805,000.00 0.00 6. Total Work Completed 35,046,217.03 7. Deductions -32,500.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 35,336,586.16 383,166.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 383,166.58