Dept. of Trans. PROGRESS Serial No. Contract No. 15-261-08-59 10-415804 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 94% Location: Federal Project: 10-MER-99-0.0/4.6 NONE Progress payment No. 038 Payment period ending: 09-20-15 SECURITY PAVING COMPANY INC 13170 TELFAIR AVENUE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 39,166,719.37 1,248,707.18 2. a. Extra Work 776,914.70 0.00 b. Adustment Comp. 428,661.36 7,899.37 3. Materials on Hand 74,898.41 64,192.38 4. Earned Subject to Retention 40,447,193.84 1,320,798.93 5. Mobilization 805,000.00 0.00 6. Total Work Completed 41,177,295.43 7. Deductions -1,031,441.40 -645,417.77 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 40,220,752.44 675,381.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 675,381.16