Dept. of Trans. PROGRESS Serial No. Contract No. 16-111-13-44 10-415804 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 99% Location: Federal Project: 10-MER-99-0.0/4.6 NONE Progress payment No. 046 Payment period ending: 04-20-16 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,807,874.67 52,370.53 2. a. Extra Work 1,148,171.16 0.00 b. Adustment Comp. 391,262.05 0.00 3. Materials on Hand 4. Earned Subject to Retention 42,347,307.88 52,370.53 5. Mobilization 805,000.00 0.00 6. Total Work Completed 43,152,307.88 7. Deductions -61,782.67 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 43,090,525.21 62,370.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 62,370.53