Dept. of Trans. PROGRESS Serial No. Contract No. 08-329-10-06 10-444204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 21% 10-ALP-88-1.9/ .0 Federal Project: NONE Progress payment No. 05 Payment period ending: 11-20-08 YOUNGER GENERAL CONTRACTORS INC 3195 FITZGERALD ROAD RANCHO CORDOVA CA 95742 Escrow No. 02393 Total Estimate This Estimate 1. Contract Itms Without Mobil. 762,987.16 106,621.43 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 762,987.16 106,621.43 5. Mobilization 6. Total Work Completed 762,987.16 7. Deductions -37,000.00 0.00 8. a.Contract Retentions -76,298.72 -10,662.15 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 649,688.44 95,959.28 10. Reduction Amt to Escrow 11. Payment to Escrow 76,290.00 12. Net Pymt. this Estimate 95,959.28