Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-201-09-29 10-444204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-ALP-88-1.9/ .0 Federal Project: NONE Progress payment No. 35 Payment period ending: 06-21-11 YOUNGER GENERAL CONTRACTORS INC 3195 FITZGERALD ROAD RANCHO CORDOVA CA 95742 Escrow No. 02393 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,746,549.22 0.00 2.a. Extra Work 642,188.61 199.78 b. Adjustment Comp. 365,335.69 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,754,073.52 199.78 5. Mobilization 6. Total Work Completed 6,754,073.52 7. Deductions 0.00 5,000.00 8. a.Contract Retentions -334,230.49 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 334,230.49 0.00 9. Total pay to Contractor 6,754,073.52 5,199.78 10. Reduction Amt to Escrow -334,230.00 0.00 11. Payment to Escrow 334,230.00 12. Net Pymt. this Estimate 5,199.78