Dept. of Trans. PROGRESS Serial No. Contract No. 01-173-13-11 10-460804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 100% 10-SJ-5-10.7/R22.5 Federal Project: ACIM-005-6(298) ACIM-005-6(298) Progress payment No. 25 Payment period ending: 06-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01477 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,741,278.18 8,707.02 2.a. Extra Work 303,851.73 -160,325.53 b. Adjustment Comp. 986,403.67 185,463.50 3. Materials on Hand 228,069.16 0.00 4. Earned Subject to Retention 14,259,602.74 33,844.99 5. Mobilization 6. Total Work Completed 14,031,533.58 7. Deductions 8. a.Contract Retentions -712,980.14 -1,692.25 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,546,622.60 32,152.74 10. Reduction Amt to Escrow 11. Payment to Escrow 712,980.00 12. Net Pymt. this Estimate 32,152.74