Dept. of Trans. PROGRESS Serial No. Contract No. 15-111-13-28 10-481004 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 79% Location: Federal Project: 10-MER-99-13.9/14.4 ACNH-P099(550) Progress payment No. 038 Payment period ending: 04-20-15 RGW CONSTRUCTION INC 550 GREENVILLE ROAD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,944,951.46 887,194.63 2. a. Extra Work 1,885,228.13 31,728.28 b. Adustment Comp. 366,015.09 0.00 3. Materials on Hand 437,106.06 -18,716.99 4. Earned Subject to Retention 19,633,300.74 900,205.92 5. Mobilization 1,825,000.00 0.00 6. Total Work Completed 21,021,194.68 7. Deductions -22,386.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,435,914.74 895,205.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 895,205.92