Dept. of Trans. PROGRESS Serial No. Contract No. 01-205-13-44 10-495404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 87% 10-MER-5-17.6/ .0 Federal Project: ACIM-005-5(125) ACIM-005-5(125) ACBH-005-5(125) Progress payment No. 04 Payment period ending: 07-20-01 VIKING CONSTRUCTION COMPANY INC 11050 D FOLSOM BLVD RANCHO CORDOVA CA 95670 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 464,504.24 116,328.00 2.a. Extra Work 116.37 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 464,620.61 116,328.00 5. Mobilization 71,000.00 3,550.00 6. Total Work Completed 535,620.61 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -23,231.03 -5,816.40 b. Unsatisfactory Prog. -5,816.40 -5,816.40 c. Reduction after 95% Comp. 9. Total pay to Contractor 496,573.18 98,245.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 98,245.20