Dept. of Trans. PROGRESS Serial No. Contract No. 01-296-13-56 10-495404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 100% 10-MER-5-17.6/ .0 Federal Project: ACIM-005-5(125) ACIM-005-5(125) ACBH-005-5(125) Progress payment No. 06 Payment period ending: 10-20-01 VIKING CONSTRUCTION COMPANY INC 11050 D FOLSOM BLVD RANCHO CORDOVA CA 95670 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 632,702.84 56,030.00 2.a. Extra Work 10,859.26 10,742.89 b. Adjustment Comp. -1,070.00 -1,070.00 3. Materials on Hand 4. Earned Subject to Retention 642,492.10 65,702.89 5. Mobilization 71,000.00 0.00 6. Total Work Completed 713,492.10 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -32,124.61 -3,285.15 b. Unsatisfactory Prog. 0.00 11,424.83 c. Reduction after 95% Comp. 9. Total pay to Contractor 681,367.49 83,842.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 83,842.57