Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 01-338-12-45 10-495404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-MER-5-17.6/ .0 Federal Project: ACIM-005-5(125) ACIM-005-5(125) ACBH-005-5(125) Progress payment No. 07 Payment period ending: 11-13-01 VIKING CONSTRUCTION COMPANY INC 11050 D FOLSOM BLVD RANCHO CORDOVA CA 95670 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 638,302.84 5,600.00 2.a. Extra Work 18,859.26 8,000.00 b. Adjustment Comp. -1,070.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 656,092.10 13,600.00 5. Mobilization 71,000.00 0.00 6. Total Work Completed 727,092.10 7. Deductions -17,000.00 -17,000.00 8. a.Contract Retentions -32,124.61 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 32,124.61 32,124.61 9. Total pay to Contractor 710,092.10 28,724.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 28,724.61