Dept. of Trans. SEMI-FINAL Serial No. Contract No. 01-354-13-26 10-495404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-MER-5-17.6/ .0 Federal Project: ACIM-005-5(125) ACIM-005-5(125) ACBH-005-5(125) Progress payment No. 08 Payment period ending: 11-13-01 VIKING CONSTRUCTION COMPANY INC 11050 D FOLSOM BLVD RANCHO CORDOVA CA 95670 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 638,302.84 0.00 2.a. Extra Work 23,504.25 4,644.99 b. Adjustment Comp. -1,070.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 660,737.09 4,644.99 5. Mobilization 71,000.00 0.00 6. Total Work Completed 731,737.09 7. Deductions -17,000.00 0.00 8. a.Contract Retentions -32,124.61 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 32,124.61 0.00 9. Total pay to Contractor 714,737.09 4,644.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,644.99