Dept. of Trans. PROGRESS Serial No. Contract No. 04-237-08-32 10-4A0004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 55% 10-TUO-120-R44.8/R0.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 08-20-04 TRUESDELL CORPORATION OF CALIFORNIA INC 3529 E WOOD STREET PHOENIX AZ 85040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 137,815.50 12,283.20 2.a. Extra Work 3,232.87 2,398.01 b. Adjustment Comp. 3. Materials on Hand 95,000.00 95,000.00 4. Earned Subject to Retention 236,048.37 109,681.21 5. Mobilization 18,200.00 910.00 6. Total Work Completed 159,248.37 7. Deductions 8. a.Contract Retentions -11,802.42 -3,260.68 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 242,445.95 107,330.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 107,330.53