Dept. of Trans. PROGRESS Serial No. Contract No. 01-024-07-05 11-001934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 33% 11-SD-125-12.1/13.7 Federal Project: ACNH-P125(13) Progress payment No. 16 Payment period ending: 01-20-01 MYERS AND ROADWAY JV P. O. BOX 2948 RANCHO CORDOVA, CA 95741 Escrow No. 01381 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,809,538.12 80,073.43 2.a. Extra Work 416,438.93 18,936.74 b. Adjustment Comp. 113,445.98 -836.15 3. Materials on Hand 130,803.47 17,160.95 4. Earned Subject to Retention 6,470,226.50 115,334.97 5. Mobilization 1,520,507.30 0.00 6. Total Work Completed 7,859,930.33 7. Deductions -62,991.34 -3,007.34 8. a.Contract Retentions -404,509.01 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,523,233.45 112,327.63 10. Reduction Amt to Escrow 11. Payment to Escrow 404,500.00 12. Net Pymt. this Estimate 112,327.63