Dept. of Trans. PROGRESS Serial No. Contract No. 02-023-13-54 11-001934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 72% 11-SD-125-12.1/13.7 Federal Project: ACNH-P125(13) Progress payment No. 29 Payment period ending: 01-20-02 MYERS AND ROADWAY JV P. O. BOX 2948 RANCHO CORDOVA, CA 95741 Escrow No. 01381 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,850,107.09 1,094,597.57 2.a. Extra Work 2,379,796.44 147,579.03 b. Adjustment Comp. 734,689.58 0.00 3. Materials on Hand 116,803.91 70,610.82 4. Earned Subject to Retention 19,081,397.02 1,312,787.42 5. Mobilization 1,600,534.00 0.00 6. Total Work Completed 20,565,127.11 7. Deductions -159,900.21 10,000.00 8. a.Contract Retentions -954,069.85 -65,639.37 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,567,960.96 1,257,148.05 10. Reduction Amt to Escrow 11. Payment to Escrow 954,060.00 12. Net Pymt. this Estimate 1,257,148.05