Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 02-094-13-25 11-001934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 78% 11-SD-125-12.1/13.7 Federal Project: ACNH-P125(13) Progress payment No. 33 Payment period ending: 03-20-02 MYERS AND ROADWAY JV P. O. BOX 2948 RANCHO CORDOVA, CA 95741 Escrow No. 01381 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,686,468.74 0.00 2.a. Extra Work 3,127,790.58 313,685.61 b. Adjustment Comp. 752,939.70 -5,931.60 3. Materials on Hand 110,160.53 74,171.82 4. Earned Subject to Retention 20,677,359.55 381,925.83 5. Mobilization 1,600,534.00 0.00 6. Total Work Completed 22,167,733.02 7. Deductions -179,900.21 0.00 8. a.Contract Retentions -1,033,867.98 -19,096.29 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,064,125.36 362,829.54 10. Reduction Amt to Escrow 11. Payment to Escrow 1,033,860.00 12. Net Pymt. this Estimate 362,829.54