Dept. of Trans. PROGRESS Serial No. Contract No. 01-024-07-05 11-0019U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 46% 43% 11-SD-125-13.7/L14.0 Federal Project: ACNH-X073(43) Progress payment No. 20 Payment period ending: 01-20-01 FCI CONSTRUCTORS 12707 HIGH BLUFF DRIVE STE 13 SAN DIEGO CA 92130 Escrow No. 01266 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,723,050.98 937,075.22 2.a. Extra Work 888,147.33 11,822.58 b. Adjustment Comp. 131,227.81 -3,423.44 3. Materials on Hand 1,625,653.52 126,394.62 4. Earned Subject to Retention 25,368,079.64 1,071,868.98 5. Mobilization 5,700,000.00 0.00 6. Total Work Completed 29,442,426.12 7. Deductions -23,751.91 0.00 8. a.Contract Retentions -1,268,403.98 -53,593.45 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 29,775,923.75 1,018,275.53 10. Reduction Amt to Escrow 11. Payment to Escrow 1,268,400.00 12. Net Pymt. this Estimate 1,018,275.53