Dept. of Trans. PROGRESS Serial No. Contract No. 02-143-10-22 11-0019U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 79% 11-SD-125-13.7/L14.0 Federal Project: ACNH-X073(43) Progress payment No. 39 Payment period ending: 05-20-02 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA, CA 92083-8831 Escrow No. 01266 Total Estimate This Estimate 1. Contract Itms Without Mobil. 43,575,003.68 710,773.67 2.a. Extra Work 3,653,197.59 928,533.82 b. Adjustment Comp. 481,438.00 -2,466.71 3. Materials on Hand 1,215,206.85 -19,655.80 4. Earned Subject to Retention 48,924,846.12 1,617,184.98 5. Mobilization 6,000,000.00 0.00 6. Total Work Completed 53,709,639.27 7. Deductions -10,932.36 3,290.00 8. a.Contract Retentions -2,446,242.31 -80,859.25 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 52,467,671.45 1,539,615.73 10. Reduction Amt to Escrow 11. Payment to Escrow 2,446,240.00 12. Net Pymt. this Estimate 1,539,615.73