Dept. of Trans. PROGRESS Serial No. Contract No. 02-169-08-09 11-0019U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 82% 11-SD-125-13.7/L14.0 Federal Project: ACNH-X073(43) Progress payment No. 40 Payment period ending: 06-20-02 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA, CA 92083-8831 Escrow No. 01266 Total Estimate This Estimate 1. Contract Itms Without Mobil. 45,195,973.16 1,620,969.48 2.a. Extra Work 3,769,786.53 116,588.94 b. Adjustment Comp. 487,234.01 5,796.01 3. Materials on Hand 1,073,666.61 -141,540.24 4. Earned Subject to Retention 50,526,660.31 1,601,814.19 5. Mobilization 6,000,000.00 0.00 6. Total Work Completed 55,452,993.70 7. Deductions -10,932.36 0.00 8. a.Contract Retentions -2,526,333.02 -80,090.71 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 53,989,394.93 1,521,723.48 10. Reduction Amt to Escrow 11. Payment to Escrow 2,526,330.00 12. Net Pymt. this Estimate 1,521,723.48