Dept. of Trans. PROGRESS Serial No. Contract No. 02-204-13-51 11-0019U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 84% 11-SD-125-13.7/L14.0 Federal Project: ACNH-X073(43) Progress payment No. 41 Payment period ending: 07-20-02 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA, CA 92083-8831 Escrow No. 01266 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,505,280.87 1,309,307.71 2.a. Extra Work 3,830,497.46 60,710.93 b. Adjustment Comp. 512,884.42 25,650.41 3. Materials on Hand 1,042,960.04 -30,706.57 4. Earned Subject to Retention 51,891,622.79 1,364,962.48 5. Mobilization 6,000,000.00 0.00 6. Total Work Completed 56,848,662.75 7. Deductions -20,932.36 -10,000.00 8. a.Contract Retentions -2,594,581.14 -68,248.12 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 55,276,109.29 1,286,714.36 10. Reduction Amt to Escrow 11. Payment to Escrow 2,594,580.00 12. Net Pymt. this Estimate 1,286,714.36