Dept. of Trans. PROGRESS Serial No. Contract No. 02-295-14-45 11-0019U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-125-13.7/L14.0 Federal Project: ACNH-X073(43) Progress payment No. 44 Payment period ending: 10-20-02 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA, CA 92083-8831 Escrow No. 01266 Total Estimate This Estimate 1. Contract Itms Without Mobil. 50,370,524.31 1,101,872.25 2.a. Extra Work 4,037,017.04 19,659.53 b. Adjustment Comp. 534,133.15 12,992.12 3. Materials on Hand 869,966.00 -38,898.16 4. Earned Subject to Retention 55,811,640.50 1,095,625.74 5. Mobilization 6,000,000.00 0.00 6. Total Work Completed 60,941,674.50 7. Deductions -20,932.36 -10,000.00 8. a.Contract Retentions -2,790,582.03 -54,781.29 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 59,000,126.11 1,030,844.45 10. Reduction Amt to Escrow 11. Payment to Escrow 2,790,580.00 12. Net Pymt. this Estimate 1,030,844.45