Dept. of Trans. PROGRESS Serial No. Contract No. 02-326-14-27 11-0019U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-125-13.7/L14.0 Federal Project: ACNH-X073(43) Progress payment No. 45 Payment period ending: 11-20-02 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA, CA 92083-8831 Escrow No. 01266 Total Estimate This Estimate 1. Contract Itms Without Mobil. 51,478,668.23 1,108,143.92 2.a. Extra Work 4,127,746.90 90,729.86 b. Adjustment Comp. 545,589.14 11,455.99 3. Materials on Hand 759,977.35 -109,988.65 4. Earned Subject to Retention 56,911,981.62 1,100,341.12 5. Mobilization 6,000,000.00 0.00 6. Total Work Completed 62,152,004.27 7. Deductions -20,932.36 0.00 8. a.Contract Retentions -2,845,599.08 -55,017.05 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 60,045,450.18 1,045,324.07 10. Reduction Amt to Escrow 11. Payment to Escrow 2,845,590.00 12. Net Pymt. this Estimate 1,045,324.07