Dept. of Trans. PROGRESS Serial No. Contract No. 03-023-10-33 11-0019U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-125-13.7/L14.0 Federal Project: ACNH-X073(43) Progress payment No. 47 Payment period ending: 01-20-03 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA, CA 92083-8831 Escrow No. 01266 Total Estimate This Estimate 1. Contract Itms Without Mobil. 53,572,355.19 1,243,684.87 2.a. Extra Work 4,524,480.56 233,665.23 b. Adjustment Comp. 549,515.00 -13,711.04 3. Materials on Hand 361,768.78 -276,114.96 4. Earned Subject to Retention 59,008,119.53 1,187,524.10 5. Mobilization 6,000,000.00 0.00 6. Total Work Completed 64,646,350.75 7. Deductions -30,932.36 -10,000.00 8. a.Contract Retentions -2,950,405.98 -59,376.21 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 62,026,781.19 1,118,147.89 10. Reduction Amt to Escrow 11. Payment to Escrow 2,950,400.00 12. Net Pymt. this Estimate 1,118,147.89