Dept. of Trans. PROGRESS Serial No. Contract No. 03-112-13-10 11-0019U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-125-13.7/L14.0 Federal Project: ACNH-X073(43) Progress payment No. 50 Payment period ending: 04-20-03 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA, CA 92083-8831 Escrow No. 01266 Total Estimate This Estimate 1. Contract Itms Without Mobil. 55,264,967.17 349,467.21 2.a. Extra Work 5,173,343.07 193,119.17 b. Adjustment Comp. 596,703.75 6,255.69 3. Materials on Hand 107,245.49 -21,482.19 4. Earned Subject to Retention 61,142,259.48 527,359.88 5. Mobilization 6,000,000.00 0.00 6. Total Work Completed 67,035,013.99 7. Deductions -40,932.36 0.00 8. a.Contract Retentions -3,057,112.97 -26,367.99 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 64,044,214.15 500,991.89 10. Reduction Amt to Escrow 11. Payment to Escrow 3,057,110.00 12. Net Pymt. this Estimate 500,991.89