Dept. of Trans. PROGRESS Serial No. Contract No. 03-203-13-03 11-0019U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-125-13.7/L14.0 Federal Project: ACNH-X073(43) Progress payment No. 55 Payment period ending: 07-20-03 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA, CA 92083-8831 Escrow No. 01266 Total Estimate This Estimate 1. Contract Itms Without Mobil. 56,330,444.28 137,310.90 2.a. Extra Work 5,909,717.79 83,564.67 b. Adjustment Comp. 623,455.83 14,349.81 3. Materials on Hand 19,076.09 -5,302.67 4. Earned Subject to Retention 62,882,693.99 229,922.71 5. Mobilization 6,000,000.00 0.00 6. Total Work Completed 68,863,617.90 7. Deductions -51,812.36 0.00 8. a.Contract Retentions -3,144,134.70 -11,496.14 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 65,686,746.93 218,426.57 10. Reduction Amt to Escrow 11. Payment to Escrow 3,144,130.00 12. Net Pymt. this Estimate 218,426.57