Dept. of Trans. PROGRESS Serial No. Contract No. 03-266-13-23 11-0019U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-125-13.7/L14.0 Federal Project: ACNH-X073(43) Progress payment No. 57 Payment period ending: 09-20-03 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA, CA 92083-8831 Escrow No. 01266 Total Estimate This Estimate 1. Contract Itms Without Mobil. 56,401,099.18 26,140.76 2.a. Extra Work 6,296,129.24 69,908.45 b. Adjustment Comp. 405,315.89 -83.36 3. Materials on Hand 4. Earned Subject to Retention 63,102,544.31 95,965.85 5. Mobilization 6,000,000.00 0.00 6. Total Work Completed 69,102,544.31 7. Deductions -88,673.77 7,590.00 8. a.Contract Retentions -3,155,127.22 -4,798.30 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 65,858,743.32 98,757.55 10. Reduction Amt to Escrow 11. Payment to Escrow 3,155,120.00 12. Net Pymt. this Estimate 98,757.55